The view from across the road tonight.
For the last few months, there have been plans to upgrade the level crossing. But Roads and Maritime Services insisted that the Newell Highway be kept open, so a side track had to be constructed.
The work was ready to go in January, but got stopped by the torrential rain that flooded the site. Then they aimed for 4 am March 31, and in the meantime constructed the most expensive 4 day road I have ever seen.
We were evacuated to a motel as the work is 24 hours a day, but when we returned home this morning we discovered that there was still nothing happening as the rain yesterday again left the site too wet.
Tonight they have made a start. However RMS have expresses dissatisfaction with the signs and markings on the side track and may or may not sign off on it at 7 am tomorrow. If the RMS fail to proceed then the work is postponed until some future date.
Meanwhile if you are wondering where your bugs have gone to, we may have them here.