Home Improvements Day 15

Today was about some cleaning up work that needed to happen.

There were lots of handles, with some still to be installed. We have a total of 65 handles, inclding a dozen or so in the bedroom.

Of course the plaster had to be sanded. After running heaters all last night, the plaster was mostly dry enough, but there were patches that he needs to come back to on Monday. Thankfully, he doesn’t expect us to run the heaters all weekend.

Home Improvement Day 14

The steps at the doorway to nowhere went in today. This is a new door from the (new) kitchen to the garage. We test drove them and found them very satisfactory.

Skirting boards and cornices went in. 130 holes were drilled for the 65 handles that some lucky apprentice will get to screw in.

The plasterer was distressed to find that the plaster board was not drying, so we have heaters running to warm the house up for the comfort of the plaster. As he said, he can’t sand it until its dry, and in this cold weather it is hard to get things dry.

I paid the first payment to the builder today. It only hurt a little bit 😀